Every contractor should review these carefully before signing any construction contract.
01
Indemnification
Defines who pays when things go wrong. Broad-form indemnification shifts all liability to the contractor, even for the owner's negligence. Many states now prohibit this.
"Contractor shall indemnify and hold harmless Owner from any and all claims arising out of or related to Contractor's performance of the Work..."
NEGOTIATE FOR · Intermediate-form indemnification that limits liability to your own negligence.
02
Liquidated Damages
Pre-set daily or weekly penalties for late completion. Typically ranges from $500 to $50,000 per day depending on project size. Must be a reasonable estimate of actual damages to be enforceable.
"For each calendar day that the Work remains incomplete after the Substantial Completion date, Contractor shall pay $2,500 as liquidated damages, not as a penalty."
NEGOTIATE FOR · Caps on total LDs, mutual LDs (bonus for early completion), clear force majeure carve-outs.
03
Change Order Procedures
Defines how scope changes are documented, priced, and approved. Poorly written change order clauses lead to more disputes than any other contract provision.
"No change in the Work shall be performed without prior written authorization. Contractor shall submit a Change Order Request within 7 days of becoming aware of the changed condition."
NEGOTIATE FOR · Clear pricing methods (unit rates, T&M caps), reasonable notice periods, right to proceed under protest.
04
Dispute Resolution
Specifies how disagreements are resolved: negotiation, mediation, arbitration, or litigation. Multi-tiered resolution (negotiate → mediate → arbitrate) is considered best practice.
"Disputes shall first be submitted to the Project Executive for resolution. If unresolved within 15 days, parties shall engage in mediation before a mutually agreed mediator."
NEGOTIATE FOR · Binding arbitration over litigation (faster, cheaper), continuation of work during dispute resolution.
05
Termination Clauses
Two types: termination for cause (breach/default) and termination for convenience (owner can cancel without reason). The convenience clause is particularly dangerous for contractors.
"Owner may terminate the Contract for convenience upon 14 days' written notice. Contractor shall be compensated for Work performed plus reasonable demobilization costs."
NEGOTIATE FOR · Fair compensation including lost profits on remaining work, clear cure periods for cause termination.
06
Pay-When-Paid / Pay-If-Paid
"Pay-when-paid" means the GC pays the sub after receiving payment from the owner (timing provision). "Pay-if-paid" means the GC only pays the sub if the owner pays (condition precedent). The distinction is critical.
"Subcontractor payment is due within 7 days of Contractor's receipt of payment from Owner for the corresponding Work."
NEGOTIATE FOR · Pay-when-paid (not pay-if-paid), 30-day payment windows, lien rights preservation.
07
Retainage
A percentage (typically 5–10%) withheld from each progress payment until project completion. Retainage ties up contractor cash flow and has been increasingly regulated by state legislatures.
"Owner shall retain 10% of each progress payment. Upon Substantial Completion, retainage shall be reduced to 5%. Final retainage released within 30 days of Final Completion."
NEGOTIATE FOR · Retainage reduction at 50% completion, release at substantial completion, interest-bearing escrow.