| Concrete |
Cubic Yards |
Footings, slabs, walls, columns, beams |
3–5% |
Forgetting reinforcing steel, form ties, embeds |
| Structural Steel |
Tons |
Beams, columns, joists, decking, connections |
2–5% |
Missing connection hardware, shear studs |
| Mechanical (HVAC) |
LF / Each |
Ductwork, piping, equipment, controls |
5–10% |
Missing fittings, hangers, insulation |
| Electrical |
LF / Each |
Conduit, wire, devices, panels, fixtures |
5–10% |
Underestimating wire lengths (vertical runs) |
| Drywall / Framing |
SF / LF |
Wall area, ceiling area, soffits, bulkheads |
5–8% |
Forgetting backing, blocking, fire-rated assemblies |
| Flooring |
SF / SY |
Floor areas by finish type, transitions, base |
8–12% |
Not accounting for pattern matching waste |
| Plumbing |
LF / Each |
Piping, fixtures, valves, equipment |
5–8% |
Missing cleanouts, access panels, sleeves |