Current lead times for critical construction materials and equipment, with procurement timing recommendations.
40–52 wk
Electrical switchgear & transformers
The most constrained category in construction. Driven by data center demand, grid infrastructure spending, and semiconductor shortages in controls. Order during schematic design, not construction documents. Consider pre-purchasing before permit approval if schedule is critical.
20–32 wk
Structural steel
Mill rolling schedules, fabrication shop backlogs, and detailing capacity all contribute. Lead times spike seasonally (Q1 orders for spring construction). Place mill orders 6–8 months before erection. Lock pricing with escalation protection for orders over 16 weeks out.
16–28 wk
Elevators & escalators
Custom cabs, controls, and machine rooms require long manufacturing windows. Award elevator contracts during design development. Coordinate pit, hoistway, and machine room dimensions early — changes after ordering add 8–12 weeks.
12–20 wk
Curtain wall & glazing
Custom profiles, coated glass, and structural silicone all have independent lead times that compound. Finalize the envelope design early. Shop drawings should start during construction documents, not after permit. Stock glass colors and standard systems can reduce lead times to 8–12 weeks.
8–16 wk
HVAC equipment
Rooftop units, chillers, and air handling units vary widely by manufacturer and customization level. Standard efficiency units have shorter lead times than high-efficiency or custom configurations. Order at construction document phase for most projects.
4–8 wk
Concrete & masonry
Generally available with short lead times for standard mixes and units. Specialty concrete (high-strength, lightweight, architectural precast) and imported stone can extend to 12–16 weeks. Confirm batch plant capacity for large pours and peak-season availability.