Award · Engine

Contract Summary

Generates a 2-page executive brief of a signed contract — key terms, deadlines, payment milestones, risks — for a PM or owner who isn't going to read 40 pages.

Engine Phase: Award Runtime: 40-70 seconds Pro+

What it does

Contract Summary reads the full contract and produces a readable 2-page brief covering the parties and scope, the financial structure (contract value, retainage, pay schedule, LDs, bond and insurance), the critical dates (start, substantial completion, final completion, notice windows), the change-order process in plain language, and the top 5 risks worth watching.

Where Contract Review gives you a clause-by-clause risk register, Contract Summary gives you the one-page-rear-of-laptop reference the field PM actually keeps.

When to use it

What to upload

One signed contract. Same formats as Contract Review (PDF best, DOCX fine).

Step by step

  1. Open the engine

    Sidebar → EnginesContract Summary.

  2. Upload the contract

    Or chain from Contract Review — the contract carries forward.

  3. Run analysis

    20–40 seconds typical.

  4. Review the sections

    Output is structured into ~7 sections: parties + scope, financials, dates, deliverables, change orders, risks, notable clauses.

  5. Export PDF

    2-page formatted brief. Hand to the PM.

Understanding the results

Parties + scope

Who signed, work covered, project name, location.

Financials

Contract value, retainage %, retainage release schedule, pay-app cycle, LD rate, LD cap, bonding requirement, insurance limits summary.

Critical dates

Notice to proceed, start, substantial completion, final completion, notice-window lengths for delay / default / change.

Change-order process

Plain-language how-to for getting a change approved — who signs, what's required, default response times.

Top risks

5-item list pulled from the same pass as Contract Review — the things most worth watching during execution.

Notable clauses

Non-standard or unusual clauses worth flagging for the field team.

Every control, explained

Run analysis

One run.

Try with sample data

Bridgeport Apex subcontract summary.

Export PDF

Formatted 2-page brief.

Export XLSX

Fielded data — dates, amounts, limits — useful for plugging into a project dashboard.

Chain to PM Handoff

Full handoff bundle with all sections plus contacts and action items.

Chains

Chains into

Run Full Contract Review — Dive deeper with a clause-by-clause risk analysis of the contract.
Generate PM Handoff Report — Create a structured handoff brief with risks, deadlines, and action items.

Chained from

Generate Contract Summary — Create a concise PM-friendly summary of the key contract terms and obligations.
Generate Contract Summary — Create a concise contract summary highlighting key terms for the PM.

Exports

Troubleshooting

Dates missing in the output

Contract didn't specify them (common — dates often come from a separate schedule). Add them manually in the exported PDF, or capture them in the Schedule tracker after signing.

LD cap not found

Not all contracts cap LDs. If left blank, that's the contract's actual state — flag it as a risk for your PM.