Submittal Tracker (engine)
The Submittal Tracker engine is the extraction step that normalizes an existing submittal log into tracker records. It reads a spec section, a submittal log or a batch of individual submittals and records ball-in-court, due date, reviewer, status and revision cycles for each, ready to import into the Submittal Tracker workspace.
What is the Submittal Tracker engine?
Submittal Tracker (engine) is a narrower cousin of Submittal Extractor: it reads a submittal-focused input (spec section, existing submittal log, or batch of individual submittals) and normalizes each record with ball-in-court, due date, architect/engineer reviewer, status, and number of revision cycles. Output imports directly to the Submittal Tracker workspace.
Use this engine when you already have a partially-managed submittal process and want to import or audit state. Use Submittal Extractor when you're starting from a raw spec section.
What do I upload to the Submittal Tracker engine?
Upload an existing submittal log such as a Procore, BIM 360 or Sage export, a spec section to extract the required submittals, or a batch of individual submittals with their cover sheets.
- Existing submittal log (Procore / BIM 360 / Sage export)
- Spec section (to extract required submittals)
- Batch of individual submittal documents with their cover sheets
How do I run the Submittal Tracker engine?
To run the Submittal Tracker engine, open it, upload the source, run it, review and edit the records and import them to the tracker.
Open the engine
Sidebar → Engines → Submittal Tracker.
Upload
Log, spec, or batch.
Run
20–40 seconds.
Review + edit
Each submittal as an editable row.
Import to tracker
Merges by submittal number if already present.
How do I read the Submittal Tracker engine results?
The result is a submittal register table with ball-in-court and overdue flags.
Number, description, type, spec ref, submittal date, due date, reviewer, status, revision count.
Who currently has it — sub, GC, architect, engineer.
Items past their due date, color-coded.
Every control, explained
Run analysisOne run.
Edit rowDescription, type, reviewer, status, ball-in-court.
Import to Submittal TrackerPush to tracker; merges by submittal number.
Export PDFFormatted submittal log.
Export XLSXRaw table for external systems.
Chains
Chains into
Chained from
Exports
- PDF — submittal log.
- XLSX — raw table.
- CSV — flat list.
Troubleshooting
Engine merges by submittal number. Ensure numbers are consistent across imports.
Sources
- ER 415-1-10: Contractor Submittal ProceduresU.S. Army Corps of EngineersThe Corps of Engineers procedure for registering, reviewing and tracking contractor submittals such as shop drawings and samples.
- Summary: A201-2017, General Conditions of the Contract for ConstructionAIA Contract DocumentsThe AIA overview of the general conditions that set out the rights and duties of owner, contractor and architect.